03 June 2024

LIH's Runway 3/21 Extension Project

HDOT announced that LIH's Runway 3/21 will be extended an additional 855 feet on the approach end of Runway 3, to bring it to a length of 7,355 feet. Taxiway A will be extended to the new end of Runway 3 as well. Runway 3/21 will close, with work will be done nightly from 23:00 to 08:00. This is part of the project to work to rehabilitate LIH's runways and taxiways.

Further information in this HDOT press release.